Query DescriptionQuery DateReplyReply DateView Detail
 
Page size:
select
 726 items in 37 pages
a Notification of Award has been issued to the lowest evaluated firm,however, neither purchase order... Click on View Detail24 Jul 2018Please visit rule 35(1) of PPR-14.... Click on View Detail26 Jul 2018
PPRA Rules 59 d(iii) negotiated tendering: d(iii) ""for reasons of extreme urgency brought about by... Click on View Detail13 Jul 2018The said rule is comprehensive and easy to understand however, you are advised to discuss the matter... Click on View Detail24 Jul 2018
Aslam O Alakum Please explain 1. What is splitting of procurement? 2. What is difference between pro... Click on View Detail16 Jul 2018Please go through rule 8, 9 & 38 of PPR-14.... Click on View Detail24 Jul 2018
What is the sufficient time to issue corrigendum which mentions change in closing date of a tender?... Click on View Detail18 Jul 2018Please visit rule 25(3) & (4) Read with rule 29 of PPR-14.... Click on View Detail24 Jul 2018
1) Is bid security required in Consulting Services? 2) During the process of pre-qualification of co... Click on View Detail18 Jul 2018Please depute someone for clarification please.... Click on View Detail24 Jul 2018
If we have sent our tender advertisement via DGPR and the advertisement is published, i. Advertise... Click on View Detail18 Jul 2018Need a visit to this office with record please.... Click on View Detail24 Jul 2018
Bidding Documents uploaded of Unique Code # 103930T1707201850, Procurement Name:Procurement of Andr... Click on View Detail20 Jul 2018Call on 0322-4864228 Mr. Asad Asst. PPRA for the detail please.... Click on View Detail24 Jul 2018
Punjab Procurement Rules are applicable for the procurement of Library books or not.... Click on View Detail20 Jul 2018All public procurements shall be completed by following PPR-14.... Click on View Detail24 Jul 2018
CAN WE EDIT BIDDING DOCUMENTS AFTER ITS OPENING DATE... Click on View Detail20 Jul 2018Not allowed. Rule 25(3)(4) of PPR-14 required to be followed.... Click on View Detail24 Jul 2018
Respected ersonnel, PPRA rules are silent about period/ time of return of CDR to the bidder. If, it ... Click on View Detail05 Jul 2018It should be mentioned in bidding document and may be released after completion of work/TORs accordi... Click on View Detail12 Jul 2018
Respected Sir, Yesterday i uploaded a tender(103683T090720181404) for Frame work contract of Medicin... Click on View Detail10 Jul 2018Call on 0322-4864228 Mr. Asad Asst. PPRA for the detail please.... Click on View Detail12 Jul 2018
I am working as a PI for a government funded project at NUST. We like to purchase a specific equipme... Click on View Detail03 Jul 2018Rule 42 of PPR-14 is provided as “Decision by simple majority.- All decision of the Consultant Selec... Click on View Detail12 Jul 2018
Why rule 15 violation occur when i upload tender notice on ppra website and how to remove this viola... Click on View Detail28 Jun 2018Call on 0322-4864228 Mr. Asad Asst. PPRA for the detail please.... Click on View Detail02 Jul 2018
Can repeat orders be issued after completing the contract?... Click on View Detail23 Jun 2018The definition of repeat order and rule 59(c) (iv) of PPR-14 are provided for the guidance please lo... Click on View Detail28 Jun 2018
If only one person, submit the bid, in case of single stage two envelop,,,, can we go for the contr... Click on View Detail26 Jun 2018Go through the rule 55A of PPR-14 please.... Click on View Detail28 Jun 2018
Can we give tender notice in daily newspaper , by direct contacting the newspaper printer? Bypassing... Click on View Detail26 Jun 2018Visit rule 55 of PPR-14 please.... Click on View Detail28 Jun 2018
Procuring Agency must sent disqualification letter to all suppliers with reasons of rejection?? what... Click on View Detail20 Jun 2018Please visit rule 37 of PPR-14.... Click on View Detail22 Jun 2018
For the purchase of books, shall a procuring agency adopt open competitive bidding procedure vide PP... Click on View Detail20 Jun 2018There is no provision in PPR-14 regarding the standard schedule rates. For further discussion please... Click on View Detail22 Jun 2018
In July-2017, a contract was awarded to M/s ABC for the procurement of fifty (50) UPS against NCB. T... Click on View Detail14 Jun 2018For detail please visit this office alongwith record.... Click on View Detail20 Jun 2018
If a vendor submits his complaint to the Grievance Committee. Is it mandatory to invite him to appea... Click on View Detail19 Jun 2018Please go through rule 67 read with rule 4 of PPR-14.... Click on View Detail20 Jun 2018